Factory Acceptance Test
Verify construction, controls, vacuum performance, refrigeration operation, safety functions, documentation and representative loaded-cycle behaviour before shipment where practical.
Use this practical FAT/SAT checklist to record the agreed load, pressure pull-down, refrigeration recovery, controls, safety functions, documentation and repeated-cycle performance before shipment and again during site commissioning.
Record the product, packaging, batch mass, entering temperature, target temperature, required cycle interval, electrical supply, site ambient conditions and any agreed automation or data-logging functions. Final acceptance criteria should match the duty used for the quotation and design review.
Verify construction, controls, vacuum performance, refrigeration operation, safety functions, documentation and representative loaded-cycle behaviour before shipment where practical.
Repeat the relevant acceptance checks after installation using the actual site utilities, ambient conditions, handling arrangement and production interfaces.
Where the project interfaces with conveyors, supervisory controls, refrigeration plant or other automation, verify those interfaces under the agreed operating sequence.
Confirm measured electrical supply and any condenser, cooling-water, compressed-air and drainage requirements under real site conditions.
Check pallet/trolley loading routes, chamber clearances, doors, conveyors and operating access against the final installation.
Verify the agreed sequence with conveyors, external refrigeration equipment, supervisory systems or remote monitoring where these form part of the project.
Repeat representative product cycles and retain temperatures, pressure trend, cycle duration and any deviations from the FAT baseline.
Record each pass/fail result, any deviation, corrective action, retest result and final sign-off. Keep the final acceptance records with the commissioning and maintenance documentation.
For automation-system FAT, SAT and site-integration testing, the ISA-105 series includes ANSI/ISA-62381-2026 / IEC 62381:2024. Project-specific vacuum, refrigeration, product-performance and mechanical criteria still need to be defined for the actual cooler and application.
Structure the product, load, utilities, controls and project requirements that should feed the acceptance criteria.
Build the specification → Loaded trialsDefine the commercial packaging and pallet configuration that should be represented during loaded testing.
Review packaging → Production targetTranslate batch size and cycle assumptions into the repeated-cycle target that needs to be demonstrated.
Check throughput → Evidence baseCross-check product suitability, packaging assumptions and published evidence before converting them into acceptance criteria.
Review independent sources →Product, packaging, batch mass, temperature duty, required throughput, installation country and site utilities provide the starting point for a project-specific FAT/SAT schedule.