Factory acceptance & commissioning

Prove the vacuum cooler against the real production duty before handover.

Use this practical FAT/SAT checklist to record the agreed load, pressure pull-down, refrigeration recovery, controls, safety functions, documentation and repeated-cycle performance before shipment and again during site commissioning.

Start with the acceptance basis

Testing only has meaning when the pass/fail criteria are agreed first.

Record the product, packaging, batch mass, entering temperature, target temperature, required cycle interval, electrical supply, site ambient conditions and any agreed automation or data-logging functions. Final acceptance criteria should match the duty used for the quotation and design review.

FAT

Factory Acceptance Test

Verify construction, controls, vacuum performance, refrigeration operation, safety functions, documentation and representative loaded-cycle behaviour before shipment where practical.

SAT

Site Acceptance Test

Repeat the relevant acceptance checks after installation using the actual site utilities, ambient conditions, handling arrangement and production interfaces.

SIT

Site Integration Test

Where the project interfaces with conveyors, supervisory controls, refrigeration plant or other automation, verify those interfaces under the agreed operating sequence.

Checklist

Factory acceptance test — before shipment

01 · Design duty

Confirm the test basis

  • ☐ Product and packaging recorded
  • ☐ Pallet/trolley format and batch mass recorded
  • ☐ Entering and target product temperatures recorded
  • ☐ Required cycle time / cycles per hour recorded
  • ☐ Destination voltage, frequency, phase and ambient conditions confirmed
02 · Chamber

Inspect fabrication and sealing

  • ☐ Chamber, floor, rails and loading clearances inspected
  • ☐ Door alignment and gasket compression checked
  • ☐ Drain and condensate arrangements checked
  • ☐ Door safety/interlock operation verified
03 · Vacuum system

Record pull-down performance

  • ☐ Pump make/model and motor details recorded
  • ☐ Empty-chamber pull-down recorded
  • ☐ Representative loaded pull-down recorded
  • ☐ Valve sequencing checked
  • ☐ Vacuum hold/leak test result retained
04 · Refrigeration

Check recovery and stability

  • ☐ Refrigerant/specification confirmed for destination
  • ☐ Evaporator and condensate removal checked
  • ☐ Key operating temperatures/pressures recorded
  • ☐ Repeated-cycle recovery checked
05 · Controls

Verify instrumentation and safety

  • ☐ Pressure transmitter checked against reference
  • ☐ Product probes checked against reference
  • ☐ HMI language, units and setpoints verified
  • ☐ Alarms, emergency stops and fault recovery tested
  • ☐ Data logging / USB / remote functions checked where specified
06 · Product trial

Test the real load

  • ☐ Product, packaging and probe positions documented
  • ☐ Starting and final temperatures recorded
  • ☐ Total cycle duration recorded
  • ☐ Temperature variation across the load reviewed
  • ☐ Product-quality observations retained
07 · Throughput

Verify repeated cycles

  • ☐ Consecutive cycles run where throughput is critical
  • ☐ Pump recovery between loads confirmed
  • ☐ Refrigeration recovery between loads confirmed
  • ☐ Required production interval demonstrated or exceptions recorded
08 · Documentation

Collect the handover pack

  • ☐ Final GA drawing
  • ☐ Electrical drawings / I/O information
  • ☐ Refrigeration schematic / charge information
  • ☐ Vacuum pump manuals
  • ☐ PLC/HMI backup and agreed software access
  • ☐ Spares and maintenance schedule
  • ☐ FAT report and punch list
Site acceptance

Repeat the tests that depend on the real installation.

Utilities

Confirm measured electrical supply and any condenser, cooling-water, compressed-air and drainage requirements under real site conditions.

Handling interfaces

Check pallet/trolley loading routes, chamber clearances, doors, conveyors and operating access against the final installation.

Integrated controls

Verify the agreed sequence with conveyors, external refrigeration equipment, supervisory systems or remote monitoring where these form part of the project.

Loaded production trial

Repeat representative product cycles and retain temperatures, pressure trend, cycle duration and any deviations from the FAT baseline.

Acceptance records

Close the project with evidence, not assumptions.

Record each pass/fail result, any deviation, corrective action, retest result and final sign-off. Keep the final acceptance records with the commissioning and maintenance documentation.

For automation-system FAT, SAT and site-integration testing, the ISA-105 series includes ANSI/ISA-62381-2026 / IEC 62381:2024. Project-specific vacuum, refrigeration, product-performance and mechanical criteria still need to be defined for the actual cooler and application.

Review the ISA-105 standards overview →

01AgreeDefine measurable criteria before testing.
02TestRecord the real conditions and measured result.
03ResolveTrack deviations and corrective actions.
04Sign offRetain the final evidence with the handover pack.